Yargıtay General Assembly of Civil Chambers, E.2025/28, K.2026/124, 25.02.2026.
The dispute concerned the contractor’s claim for the price of two units under a construction contract in return for land share. The General Assembly held that tying contractual delivery to an occupancy permit constitutes a written evidence agreement. Where turnkey delivery is required, contractual delivery is not completed without that permit.